ORDER authorizing and approving Change Order No. 1 with LJ Construction Inc., for the Firetower Road Sewer System Improvements ARPA/MCWI project to incorporate boring requirements associated with a permit to cross two gas lines, with a change order increase of $24,890.00 fully covered by available grant funding, as reviewed and recommended by Chiniche Engineering & Surveying, and further authorizing the Board President to execute all documents.

Order Passed Introduced June 24, 2025

What this record is

Held by
LJ Construction Inc 7 records across this site
Amount
$25K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

LJ Construction Inc also holds

ORDER approving final project closeout documents for ARPA/MCWI Firetower Sewer Project with LJ Construction, Inc., as recommended by Chiniche Engineer… $148K Harrison County, MS ORDER approving Change Order 4 with LJ Construction, for the ARPA/MWCI Firetower Road Sewer System Improvements Projects, adding 30 calendar days to t… Harrison County, MS ORDER approving Change Order 3 for the ARPA / MCWI Firetower Sewer Project with LJ Construction Inc., for an increase in time of 90 days relating to d… Harrison County, MS ORDER approving payment of claims listed: a) $376,848.12 to LJ Construction, Inc., Pay Application No. 5, ARPA Firetower Road Sewer project, payable f… $370K Harrison County, MS ends Jan 31, 2026 ORDER approving Change Order 2 with LJ Construction Inc., for the ARPA/MCWI Firetower Road Sewer System Improvements Project, to include a pump statio… $38K Harrison County, MS

All 7 records for LJ Construction Inc →

Committee
Engineering
Introduced
June 24, 2025
On agenda
July 7, 2025
Passed
July 7, 2025