25-2291
ORDER approving Change Order 2 with LJ Construction Inc., for the ARPA/MCWI Firetower Road Sewer System Improvements Project, to include a pump station and service connection for commercial use (Currently NECOs) at the north end of the project. Change Order included an increase of $37,573.25 and 10 additional contract days and grant funds are available to fully cover the cost. Authorize the Board President to execute documents.
What this record is
- Held by
- LJ Construction Inc 7 records across this site
- Amount
- $38K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
LJ Construction Inc also holds
ORDER approving final project closeout documents for ARPA/MCWI Firetower Sewer Project with LJ Construction, Inc., as recommended by Chiniche Engineer… ORDER approving Change Order 4 with LJ Construction, for the ARPA/MWCI Firetower Road Sewer System Improvements Projects, adding 30 calendar days to t… ORDER approving Change Order 3 for the ARPA / MCWI Firetower Sewer Project with LJ Construction Inc., for an increase in time of 90 days relating to d… ORDER approving payment of claims listed: a) $376,848.12 to LJ Construction, Inc., Pay Application No. 5, ARPA Firetower Road Sewer project, payable f… ORDER authorizing and approving Change Order No. 1 with LJ Construction Inc., for the Firetower Road Sewer System Improvements ARPA/MCWI project to in…All 7 records for LJ Construction Inc →
- Committee
- Engineering
- Introduced
- December 2, 2025
- On agenda
- December 8, 2025
- Passed
- December 8, 2025