docketcity.com
G24-4576

Consideration of Change Order No. 2 to the contract with Crossland Heavy Contractors, Inc. for construction of the Black Bob Pump Station Site and Piping Improvements Project, PN 5-RF-001-22.

Council Consent Passed Introduced August 8, 2024

What this record is

Held by
Crossland Heavy Contractors, Inc 8 records across this site
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Crossland Heavy Contractors, Inc also holds

Consideration of Amendment No. 4 with Crossland Heavy Contractors, Inc. for construction of the West Cedar Creek Sewer Interceptor Project, PN 1-C-011… Olathe, KS Consideration of Amendment No. 3 with Crossland Heavy Contractors, Inc. for construction of the West Cedar Creek Sewer Interceptor Project, 1-C-011-24… Olathe, KS Consideration of Amendment No. 2 with Crossland Heavy Contractors, Inc. for construction of the West Cedar Creek Sewer Interceptor Project, 1-C-011-24… Olathe, KS Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Crossland Heavy Contractors, Inc. for construction of the Renner Pum… Olathe, KS Consideration of Amendment No. 1 with Crossland Heavy Contractors, Inc. for construction of the West Cedar Creek Sewer Interceptor Project, 1-C-011-24… Olathe, KS

All 8 records for Crossland Heavy Contractors, Inc →

Committee
City Council
Requested by
Public Works
Introduced
August 8, 2024
On agenda
August 20, 2024
Passed
August 20, 2024

Where it was heard

City Council Aug 20, 2024 approved Pass