docketcity.com
G24-4363

Award of contract to Crossland Heavy Contractors, Inc. for construction of the Olathe WTP2 Chemical Feed and Electrical Modifications and Improvements - Control Room Expansion and Filter Building Fluoride Room Rehab Project, PN 5-C-026-20 & 5-C-028-20.

Council Consent Passed Introduced April 28, 2024

What this record is

Held by
Crossland Heavy Contractors, Inc 8 records across this site
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Crossland Heavy Contractors, Inc also holds

Consideration of Amendment No. 4 with Crossland Heavy Contractors, Inc. for construction of the West Cedar Creek Sewer Interceptor Project, PN 1-C-011… Olathe, KS Consideration of Amendment No. 3 with Crossland Heavy Contractors, Inc. for construction of the West Cedar Creek Sewer Interceptor Project, 1-C-011-24… Olathe, KS Consideration of Amendment No. 2 with Crossland Heavy Contractors, Inc. for construction of the West Cedar Creek Sewer Interceptor Project, 1-C-011-24… Olathe, KS Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Crossland Heavy Contractors, Inc. for construction of the Renner Pum… Olathe, KS Consideration of Amendment No. 1 with Crossland Heavy Contractors, Inc. for construction of the West Cedar Creek Sewer Interceptor Project, 1-C-011-24… Olathe, KS

All 8 records for Crossland Heavy Contractors, Inc →

Committee
City Council
Requested by
Public Works
Introduced
April 28, 2024
On agenda
May 7, 2024
Passed
May 7, 2024

Where it was heard

City Council May 7, 2024 approved Pass