Approve the award of Change Order #1 to Contract 24-153, Central Elevated Tank Construction, to Phoenix Fabricators and Erectors LLC for an additional 91 days

Procurement Change Order Passed Introduced March 20, 2026

What this record is

Held by
Phoenix Fabricators and Erectors LLC 4 records across this site
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Phoenix Fabricators and Erectors LLC also holds

Approve the award of Bid 24-153, Central Elevated Tank, to Phoenix Fabricators and Erectors LLC for an amount not to exceed $5,368,759, plus a 3% cont… $5.37M Naperville, IL Change Order No. 2 with Phoenix Fabricators and Erectors, LLC in the amount of $47,820.00 for Project No. WA1910. $48K Fargo, ND Change Order No. 1 with Phoenix Fabricators and Erectors, LLC in the amount of $61,877.55 for Project No. WA1910. $62K Fargo, ND
Committee
City Council
Requested by
Water Utilities