South Park Avenue Pedestrianization Project, Final Balancing Change Order No. 3 Reflecting a decrease to the contract with R.W. Dunteman Company in the amount of $108,635.58. This Change Order is based upon final measured quantities. (DISTRICT #1)

Resolution Passed Introduced August 13, 2025

What this record is

Held by
Dunteman Company 8 records across this site
Amount
$109K
Runs until
no end date published in this record
Type
amendment

Read automatically from the title of the official record. The source document below is authoritative.

Dunteman Company also holds

FY2026 Asphalt Roadway Program Award of a contract to R.W. Dunteman Company, the lowest responsible bidder of four (4) bids received, in the amount of… $1.39M Lombard, IL Downtown Sidewalk Improvement Project, Final Balancing Change Order No. 6 Reflecting a decrease to the contract with R.W. Dunteman Company, in the amo… $105K Lombard, IL DT-R-0173B-22 – Amendment to Resolution DT-R-0173A-22, issued to R.W. Dunteman Company for the 2022 Pavement Maintenance (North) Program, Section 22-P… $48K DuPage County, IL East St. Charles Road Sidewalk Improvement Project, Change Order No. 1 Approving an extension of contract with R.W. Dunteman Company. This Change Orde… Lombard, IL Downtown Sidewalk Improvement Project, Final Balancing Change Order No. 5 Reflecting a decrease to the contract with R.W. Dunteman Company in the amou… $116K Lombard, IL

All 8 records for Dunteman Company →

Committee
Village Board of Trustees
Requested by
Public Works Department
Introduced
August 13, 2025
Passed
September 18, 2025
Enacted
September 18, 2025
Enactment no.
R 46-25