South Park Avenue Pedestrianization Project Change Order No. 2 Reflecting an increase of $56,192.70 to the contract with R.W. Dunteman Company. This increase reflects additional work improving the sanitary sewer system and the increase of material associated with the concrete roadway, temporary traffic signal and temporary lighting. (DISTRICT #1)
What this record is
- Held by
- Dunteman Company 8 records across this site
- Amount
- $56K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Dunteman Company also holds
FY2026 Asphalt Roadway Program Award of a contract to R.W. Dunteman Company, the lowest responsible bidder of four (4) bids received, in the amount of… South Park Avenue Pedestrianization Project, Final Balancing Change Order No. 3 Reflecting a decrease to the contract with R.W. Dunteman Company in th… Downtown Sidewalk Improvement Project, Final Balancing Change Order No. 6 Reflecting a decrease to the contract with R.W. Dunteman Company, in the amo… DT-R-0173B-22 – Amendment to Resolution DT-R-0173A-22, issued to R.W. Dunteman Company for the 2022 Pavement Maintenance (North) Program, Section 22-P… East St. Charles Road Sidewalk Improvement Project, Change Order No. 1 Approving an extension of contract with R.W. Dunteman Company. This Change Orde…All 8 records for Dunteman Company →
- Committee
- Village Board of Trustees
- Requested by
- Public Works Department
- Introduced
- April 3, 2024
- Passed
- May 16, 2024
- Enacted
- May 16, 2024
- Enactment no.
- R 26-24