2012 Water System Improvements Project Motion to award a construction contract with K.M. Davis Contracting Co., Inc., in the amount of $506,245, for the 2012 Water System Improvements Project.

Motion BLW-Water and Sewer Introduced May 22, 2012

What this record is

Held by
Davis Contracting Co., Inc 6 records across this site
Amount
$506K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Davis Contracting Co., Inc also holds

ATH2024-038 Authorization for the purchase of material from Southern Pipe and Supply (1850 Freeman Parkway SE, Mableton, GA, 30126) in the amount of $… $151K Smyrna, GA Kennesaw Avenue Water Line Replacement Phase I Motion to award a construction contract with K.M. Davis Contracting Co, Inc. in the amount of $844,180 … $844K Marietta, GA Kirkpatrick Drive Area Water System Improvements Project/ Contract Award Motion to award a construction contract to K.M. Davis Contracting Co, Inc. in… $930K Marietta, GA Tower Road Area Utility Relocations/ Change Order No. 1 (Final) Motion to approve change order No. 1 (Final) to the contract with K.M. Davis Contracti… $62K Marietta, GA Roswell Street Improvements/ Alexander Street to Olive Street - 12" Water Main Utility Relocations Project Motion for approval to award a construction… $316K Marietta, GA
Committee
BOARD OF LIGHTS AND WATER
Introduced
May 22, 2012
On agenda
June 11, 2012
Passed
June 11, 2012