2026-1153
Commission District(s): All CO - Change Order No. 2 to Contract No. 1381109 Design/Build Services for Snapfinger Advanced Wastewater Treatment Facility (SFAWTF) Expansion - Phase 3B Project (UV Disinfection System): For use by the Department of Watershed Management (DWM) to obtain design services, furnishing, permitting and constructing of UV system. Seeking to increase contract scope of work, funding and performance time. Awarded to Morgan Contracting, Inc. Amount Not to Exceed $394,309.31.
What this record is
- Held by
- Morgan Contracting, Inc 3 records across this site
- Amount
- $394K
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Morgan Contracting, Inc also holds
Commission District(s): All CO - Change Order No. 1 to Contract No. 1381109 Design/Build Services for Snapfinger Advanced Wastewater Treatment Facilit… Commission District(s): All RFP - Request for Proposals No. 23-500650 Design Build Services for Snapfinger Advanced Wastewater Treatment Facility Expa…- Committee
- Board of Commissioners
- Requested by
- Purchasing & Contracting
- Introduced
- July 13, 2026
- On agenda
- August 25, 2026