2025-1551
Commission District(s): All CO - Change Order No. 1 to Contract No. 1381109 Design/Build Services for Snapfinger Advanced Wastewater Treatment Facility Expansion - Phase 3B Project (UV Disinfection System): for use by the Department of Watershed Management (DWM). This contract consists of providing the design, and furnishing, permitting, constructing, starting up, and successfully commissioning the ultraviolet (UV) disinfection process at the Snapfinger Advanced Wastewater Treatment Facility (AWTF). This request seeks to ratify a previously provided contract term increase. This request also seeks to increase contract scope of work, funding, and contract term through December 31, 2028. Awarded to Morgan Contracting, Inc. Amount Not to Exceed: $1,413,322.17.
What this record is
- Held by
- Morgan Contracting, Inc 3 records across this site
- Amount
- $1.41M
- Runs until
- December 31, 2028 2 years away date quoted from the award document
- Type
- award
- Field
- Construction
See everything else expiring in this field →
Read automatically from the title of the official record. The source document below is authoritative.
Morgan Contracting, Inc also holds
Commission District(s): All CO - Change Order No. 2 to Contract No. 1381109 Design/Build Services for Snapfinger Advanced Wastewater Treatment Facilit… Commission District(s): All RFP - Request for Proposals No. 23-500650 Design Build Services for Snapfinger Advanced Wastewater Treatment Facility Expa…- Committee
- Board of Commissioners
- Requested by
- Purchasing & Contracting
- Introduced
- October 16, 2025
- On agenda
- January 13, 2026
- Passed
- January 13, 2026