Commission District(s): All CO - Change Order No. 3 to Contract No.1283955 Cooperative Agreement for Consent Decree: Trenchless Technology Rehabilitation, External Point Repairs, and Related Products and Services (OMNIA Partners Cooperative Purchasing Agreement No. R170802) [DeKalb Cooperative Agreement]: for use by the Department of Watershed Management (DWM). This contract consists of providing sewer system trenchless sewer line rehabilitation services. This request seeks to utilize the (Engineering News Record - Construction Cost Index) to calculate and address cost increases for work completed after January 1, 2025. This request also seeks to increase the contract scope of work, funds, and contract term through December 31, 2026. Awarded to SAK Construction, LLC. Amount Not To Exceed: $14,096,700.42.
What this record is
- Held by
- SAK Construction, LLC 18 records across this site
- Amount
- $14.1M
- Runs until
- December 31, 2026 76 days — goes back out to bid date quoted from the award document
- Type
- amendment
- Field
- Construction
- Compared to
- $1.00M – $12.0M the middle half of 10 other SAK Construction, LLC contracts; median $6.89M
construction contracts in GA that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
SAK Construction, LLC also holds
RESOLUTION 2026-32: A RESOLUTION OF THE TOWN COMMISSION OF THE TOWN OF LAUDERDALE-BY-THE-SEA, FLORIDA, APPROVING A PIGGYBACK AGREEMENT WITH SAK CONSTR… Work Authorization No. SAK-U06 Trenchless Rehabilitation Services (Sewer Lining) (FY 2026 Budget Funded - Water & Sewer Enterprise Fund) - SAK Constru… Authorize the City Manager to execute the Agreement with SAK Construction, LLC for Wastewater System Rehabilitation Services on an as-needed basis in … Sponsor: Director of Water Services Department Authorizing the Manager of Procurement Services to execute an $8,500,000.00 construction contract with … Consideration of Engineer’s Estimate, acceptance of bids, and award of contract to SAK Construction, LLC for construction of the Arrowhead Truss Mains…All 18 records for SAK Construction, LLC →
- Committee
- Board of Commissioners
- Requested by
- Purchasing & Contracting
- Introduced
- October 21, 2024
- On agenda
- January 14, 2025
Where it was heard
Board of Commissioners Committee of the Whole Board of Commissioners Board of Commissioners Board of Commissioners Committee of the WholeWatch what DeKalb County buys
This is one award. DeKalb County signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.