Action to Authorize the City Manager to (1) Execute Amendment No. 1 to the Substation Agreement with 1220 Santa Clara Propco, LLC for the Memorex Junction Substation and (2) Negotiate and Execute Amendments to Other Existing Customer Substation Agreements to Allow for Load Ramp Acceleration and/or Additional Capacity, Subject to Power Availability and Incorporation of Standardized Terms for Curtailment and Other Conditions

Consent Calendar Passed Introduced March 18, 2026

What this record is

Held by
Santa Clara Propco, LLC
Runs until
no end date published in this record
Type
amendment
Field
Utilities & energy

Read automatically from the title of the official record. The source document below is authoritative.

Committee
City Council and Authorities Concurrent
Requested by
Electric
Introduced
March 18, 2026
On agenda
April 21, 2026
Passed
April 21, 2026

Where it was heard

City Council and Authorities Concurrent Apr 21, 2026 Adopted Pass