Consider recommendations regarding the Tajiguas Sanitary Landfill 2026 Access Road Extension and Site Improvements, County Project No. 828999, Third District, as follows: a) Approve the plans and specifications for the construction of the Tajiguas Sanitary Landfill 2026 Access Road Extension and Site Improvements, on file in the Public Works Department office; b) Approve and authorize the Chair to execute the Construction Contract with Toro Enterprises, Inc., the lowest responsible bidder, to construct the Tajiguas Sanitary Landfill 2026 Access Road Extension and Site Improvements for a contract term of September 1, 2026, through October 30, 2026, in the amount of $763,791.00; c) Authorize the Director of Public Works, or designee, to approve change orders for County Project No. 828999 for a contingency amount up to $50,689.55, for a total amount not to exceed $814,480.55; and d) Determine that pursuant to the California Environmental Quality Act (CEQA) Guidelines Section 15162, no substantial changes are proposed, no substantial changes in circumstances have occurred, and no new information of substantial importance regarding environmental effects of the project or of the sufficiency or feasibility of mitigation measures have occurred, and therefore the construction of the project is within the scope of the prior environmental review documents for the Tajiguas Landfill including the Tajiguas Landfill Expansion Project Environmental Impact Report (EIR) (01-EIR-05) certified by the Board of Supervisors on August 13, 2002, the Addendum to 01-EIR-05 dated November 8, 2006 and accepted by the Board of Supervisors on December 5, 2006, the Tajiguas Landfill Reconfiguration and Baron Ranch Restoration Project Subsequent EIR (08-EIR-00000-00007) certified by the Board of Supervisors on May 5, 2009 and the Tajiguas Landfill Capacity Increase Project EIR (23EIR-00001) certified by the Board of Supervisors on March 19, 2024 and no new environmental document shall be prepared for this project.

Administrative Item Agenda Ready Introduced August 6, 2026

What this record is

Held by
Toro Enterprises, Inc 25 records across this site
Amount
$814K
Runs until
October 30, 2026 14 days — goes back out to bid date quoted from the award document
Type
amendment
Field
Construction
Compared to
$260K – $3.20M the middle half of 19 other Toro Enterprises, Inc contracts; median $788K

construction contracts in CA that end within a year →
Governments publish the end date in the award. That date is when the work goes back out to bid, and it is usually stated years ahead.

Read automatically from the title of the official record. The source document below is authoritative.

Toro Enterprises, Inc also holds

Ratify an Emergency Order and Authorization of the Approval of an Agreement with Toro Enterprises, Inc. for the Emergency Conditions and Repair of the… Oxnard, CA Approval of, and Authorization to Execute, Contract Change Order No. 2 for the Pavement Resurfacing – Nyeland Acres Area Project with Toro Enterprises… $78K Ventura County, CA Receive and File Report on the Emergency Action Taken for the Peach Hill Wash Access Road Emergency Repair Project; Determine that There is a Need to … $361K Ventura County, CA Termination of the Emergency Order and Authorization of the Approval of an Agreement with Toro Enterprises, Inc. for the Emergency Sewer Collection Sy… Oxnard, CA Receive and File Report on an Emergency Contract Entered Into by the Public Works Agency Director with Toro Enterprises, Inc. for the Peach Hill Wash … Ventura County, CA

All 25 records for Toro Enterprises, Inc →

Committee
BOARD OF SUPERVISORS
Introduced
August 6, 2026
On agenda
August 18, 2026
Passed
August 18, 2026

Where it was heard

BOARD OF SUPERVISORS Aug 18, 2026 Acted on as follows: Pass

Watch what Santa Barbara County buys

This is one award. Santa Barbara County signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top