Consider recommendations regarding a First Amendment to Calle Real Water Loop Phase 2 Construction Contract; as follows: a) Approve and authorize the Chair of the Board of Supervisors to execute a First Amendment (Amendment) to Board Contract No. 24134 with Tierra Contracting, Inc. (Agreement) for the construction of the Calle Real Water Loop Phase 2 Project (Project) increasing the contract amount the Contingency Amount by $68,958.80 for an amended Contingency Amount of $159,005.30, and adding Additive Bid Item No. 1 and Additive Bid Item No. 3 in the amount of $1,379,176.00 for an increased maximum aggregate contract amount of $3,089,111.30, and extending the contract Term through December 31, 2025; b) Approve and authorize the Director of General Services, or his Assistant Director designee, to approve Change Orders under the Agreement in an aggregate amount not to exceed $159,005.30, and in accordance with Public Contract Code Section 20142; and c) Determine that the Project continues to be exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15302 of the State Guidelines for the Implementation of CEQA which consists of replacement or reconstruction of existing structures and facilities where the new structure will be located on the same site as the structure replaced and have substantially the same purpose and capacity as the structure replaced, and that a Notice of Exemption on this basis was approved by the Board on August 27, 2024 and filed.
What this record is
- Held by
- Tierra Contracting, Inc 5 records across this site
- Amount
- $159K
- Runs until
- December 31, 2025 already ended date quoted from the award document
- Type
- amendment
- Field
- Construction
- Compared to
- $159K – $2.00M the middle half of 4 other Tierra Contracting, Inc contracts; median $2.00M
construction contracts in CA that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
Tierra Contracting, Inc also holds
Consider recommendations regarding a Second Amendment to the Calle Real Water Loop Phase 2 Construction Contract, County Project 25014 (WD PRJ-000861)… Consider recommendations regarding Agreements for Fiscal Year (FY) 2025-2026 for Flood Control maintenance and Real Property services for routine work… Consider recommendations regarding a Construction Agreement for the Calle Real Water Loop Improvements Phase 2; County Project No. 19012; Second Distr… Consider recommendations regarding agreements for Routine Maintenance, Engineering, and Real Property Services for Emergency Response Efforts and As-N…- Committee
- BOARD OF SUPERVISORS
- Introduced
- August 8, 2025
- On agenda
- August 19, 2025
- Passed
- August 19, 2025
Where it was heard
BOARD OF SUPERVISORSWatch what Santa Barbara County buys
This is one award. Santa Barbara County signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.