25-0005
Request for Proposal 2360 Agreement with Leidos Engineering, LLC., Reston, Virginia, for $1,292,028 and 15 percent change order authority of $193,804 from Public Utilities Substation Transformer Upgrade Capital Account for La Colina Substation Upgrade Project for 3.5 year term with one additional two-year extension option (Ward 2)
What this record is
- Held by
- Leidos Engineering, LLC 2 records across this site
- Amount
- $1.29M
- Runs until
- December 6, 2029 3 years away calculated from the contract term stated in the record
- Type
- rfp
See everything else expiring in this field →
Read automatically from the title of the official record. The source document below is authoritative.
Leidos Engineering, LLC also holds
Approve increase to Work Order 2202776 in amount of $1,680,000 from Public Utilities Substation Transformer Upgrade Capital Account, bringing total Wo…- Committee
- City Council
- Requested by
- Public Utilities
- Introduced
- December 6, 2024
- On agenda
- January 7, 2025