ID 25-1493
Approve Contract Change Order No. 2 in the amount of $188,137.20, with no additional working days, for bid item overruns in Hot Mix Asphalt paving with Avison Construction, Incorporated, of Madera, California, for the Herndon Avenue Overlay from Valentine Avenue to Marks Avenue - Project ID PW01003 (Bid File 12500989) (Council District 2)
What this record is
- Held by
- Avison Construction, Incorporated 6 records across this site
- Amount
- $188K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Avison Construction, Incorporated also holds
Actions pertaining to the Cedar Avenue at Shields Avenue and Fountain Way Intersection Enhancements Project (Bid File 12602037) (Council District 4) 1… Actions pertaining to the North Granville Avenue Safety Improvements Project (Bid File No. 12601290): (Council District 6) 1. Adopt a finding of Categ… Approve Contract Change Order No. 03 with Avison Construction Incorporated of Madera, California in the amount of $235,536.06 with seventeen (17) addi… Approve Contract Change Order No. 5 in the amount of $122,470.55, with fifty-eight (58) additional working days for additional improvements to Les Kim… Approve Contract Change Order No. 3 in the amount of $13,554.81, with twenty-one additional working days for revisions to retaining wall improvements …- Committee
- City Council
- Requested by
- Capital Projects Department
- Introduced
- October 23, 2025
- On agenda
- November 6, 2025
- Passed
- November 6, 2025