Approve Contract Change Order No. 5 in the amount of $122,470.55, with fifty-eight (58) additional working days for additional improvements to Les Kimber Park for the installation of one monument sign, the redesign at the intersection of West Creek Village and Church Avenue, storm drain adjustments on the west side of the project, the installation of one four-inch water service and the installation of shotcrete at the play area with Avison Construction Company, Incorporated of Madera, California for the Transformative Climate Communities Park at MLK Magnet Core Project - Project ID PW00857. (Bid File 12302905) (Council District 3)

Action Item Passed Introduced July 23, 2025

What this record is

Held by
Avison Construction Company, Incorporated 6 records across this site
Amount
$122K
Runs until
Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
Type
amendment
Field
Construction
Compared to
$122K – $479K the middle half of 6 other Avison Construction Company, Incorporated contracts; median $236K

construction contracts in CA that end within a year →
Governments publish the end date in the award. That date is when the work goes back out to bid, and it is usually stated years ahead.

Read automatically from the title of the official record. The source document below is authoritative.

Avison Construction Company, Incorporated also holds

Actions pertaining to the Cedar Avenue at Shields Avenue and Fountain Way Intersection Enhancements Project (Bid File 12602037) (Council District 4) 1… $945K Fresno, CA Actions pertaining to the North Granville Avenue Safety Improvements Project (Bid File No. 12601290): (Council District 6) 1. Adopt a finding of Categ… $479K Fresno, CA Approve Contract Change Order No. 2 in the amount of $188,137.20, with no additional working days, for bid item overruns in Hot Mix Asphalt paving wit… $188K Fresno, CA Approve Contract Change Order No. 03 with Avison Construction Incorporated of Madera, California in the amount of $235,536.06 with seventeen (17) addi… $236K Fresno, CA Approve Contract Change Order No. 3 in the amount of $13,554.81, with twenty-one additional working days for revisions to retaining wall improvements … $14K Fresno, CA
Committee
City Council
Requested by
Capital Projects Department
Introduced
July 23, 2025
On agenda
August 14, 2025
Passed
August 14, 2025

Where it was heard

City Council Aug 14, 2025 APPROVED ON CONSENT CALENDAR Pass

Watch what Fresno buys

This is one award. Fresno signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top