ID 25-1034
Approve Contract Change Order No. 5 in the amount of $122,470.55, with fifty-eight (58) additional working days for additional improvements to Les Kimber Park for the installation of one monument sign, the redesign at the intersection of West Creek Village and Church Avenue, storm drain adjustments on the west side of the project, the installation of one four-inch water service and the installation of shotcrete at the play area with Avison Construction Company, Incorporated of Madera, California for the Transformative Climate Communities Park at MLK Magnet Core Project - Project ID PW00857. (Bid File 12302905) (Council District 3)
What this record is
- Held by
- Avison Construction Company, Incorporated 6 records across this site
- Amount
- $122K
- Runs until
- Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
- Type
- amendment
- Field
- Construction
- Compared to
- $122K – $479K the middle half of 6 other Avison Construction Company, Incorporated contracts; median $236K
construction contracts in CA that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
Avison Construction Company, Incorporated also holds
Actions pertaining to the Cedar Avenue at Shields Avenue and Fountain Way Intersection Enhancements Project (Bid File 12602037) (Council District 4) 1… Actions pertaining to the North Granville Avenue Safety Improvements Project (Bid File No. 12601290): (Council District 6) 1. Adopt a finding of Categ… Approve Contract Change Order No. 2 in the amount of $188,137.20, with no additional working days, for bid item overruns in Hot Mix Asphalt paving wit… Approve Contract Change Order No. 03 with Avison Construction Incorporated of Madera, California in the amount of $235,536.06 with seventeen (17) addi… Approve Contract Change Order No. 3 in the amount of $13,554.81, with twenty-one additional working days for revisions to retaining wall improvements …- Committee
- City Council
- Requested by
- Capital Projects Department
- Introduced
- July 23, 2025
- On agenda
- August 14, 2025
- Passed
- August 14, 2025
Where it was heard
City CouncilWatch what Fresno buys
This is one award. Fresno signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.