docketcity.com
ID#25-00634

Review and act on Contract Change Order No. 1 with Sabel Mechanical LLC, for the River’s Crossing Pump Station and Golf Road Pump Station Improvements project.

Discussion and Recommendation Passed Introduced April 11, 2025

What this record is

Held by
Sabel Mechanical LLC 3 records across this site
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Sabel Mechanical LLC also holds

Contract 106-24 was awarded to Sabel Mechanical LLC for $392,100 with a contingency of $58,815 for Channel Aeration Blower Replacement. Change orders … $448K Appleton, WI Review and possible action on Contract Change Order No. 2 with Sabel Mechanical LLC, for the River’s Crossing Pump Station and Golf Road Pump Station … Waukesha, WI
Committee
City Council
Introduced
April 11, 2025
On agenda
May 6, 2025
Passed
May 6, 2025

Where it was heard

City Council May 6, 2025 Board of Public Works Apr 17, 2025 recommended for Council Consent Pass