1206-25
Subject: Consideration of Change Order No. 3 on Contract W-25-4, 2025 Lead Service Replacement Project, Miller Pipeline (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in a net increase of $15,547.44, bringing the total contract amount to $3,153,841.97.
What this record is
- Amount
- $3.15M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Waterworks Commission
- Introduced
- November 13, 2025
- Passed
- November 19, 2025