Subject: Consideration of Change Order No. 3 on Contract W-25-3, Water Main Replacement - Phase 2, Reesman's Excavating & Grading (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in an increase of $22,688.95, bringing the total contract amount to $1,288,297.20.

Communication Passed Introduced October 13, 2025

What this record is

Amount
$1.29M
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Waterworks Commission
Introduced
October 13, 2025
Passed
October 15, 2025