Subject: Final Payment Request on Contract W-24-1, 2024 Lead Service Replacements - Phase 2, Miller Pipeline (Contractor) Staff Recommendation: To Approve Fiscal Note: Contract W-24-1 is complete at a final cost of $913,857.21. The Contract achieved a 14.5% RWP compliance rate compared to the 20% RWP goal.

Communication Passed Introduced November 8, 2024

What this record is

Amount
$914K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Waterworks Commission
Introduced
November 8, 2024
Passed
November 20, 2024