docketcity.com
0823-24

Subject: Communication sponsored by Alder Jones, on behalf of the Department of Public Works, submitting final payment for Contract 2023029 - Racine Public Works Transfer Station, Bukacek Construction, Contractors. Recommendation of the Public Works and Services Committee on 09.24.24: That the work completed by Bukacek Construction, on Contract 2023029 - Racine Public Works Transfer Station, be accepted and final payment authorized for a total contract amount of $4,803,625.61. Final payment to include retainage. Fiscal Note: Contract 2023029 was authorized under Resolution No. 0314-23 on April 17, 2023.

Communication In Committee Introduced September 17, 2024

What this record is

Amount
$4.80M
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Public Works and Services Committee
Introduced
September 17, 2024