Subject: Communication sponsored by Alder Harmon, requesting to rescind Resolution 0114-26 due to an error in Change Order No. 4 under Contract No. 2024107 (with Berglund Construction Co. for tuckpointing work). Staff Recommendation to the Public Works and Services Committee on 08.25.26: To approve rescinding Item No. 0114-26 to restore the total contract award amount. Fiscal Note: N/A

Communication In Committee Introduced July 28, 2026

What this record is

Held by
Berglund Construction Co 16 records across this site
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Berglund Construction Co also holds

Subject: Communication sponsored by Alder Harmon, submitting final payment for Contract 2025146 - Racine Multi-Site Tuckpointing, Berglund Constructio… $1.00M Racine, WI Subject: Communication sponsored by Alder Harmon, requesting approval of final payment to Berglund Construction Co. for Contract No. 2024107 for tuckp… $25K Racine, WI Subject: Communication sponsored by Alder Pabon,submitting bid results for Contract 10141535 - Phase III Transit Center Renovations & Repairs. Recomme… $825K Racine, WI Resolution approving an award of contract to Berglund Construction Company (Milwaukee, WI) for facade repair at Hillside Terrace in the amount of $224… $225K Milwaukee, WI Resolution approving an award of contract to Berglund Construction Company (Milwaukee, WI) for façade repair at Locust Court in the amount of $499,000… $499K Milwaukee, WI

All 16 records for Berglund Construction Co →

Committee
Public Works and Services Committee
Introduced
July 28, 2026