0626-26
Subject: Consideration of Change Order No. 1 on Contract EqRa-001, 2026 Lead Service Line Replacement, Miller Pipeline (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in a decrease of $1,669,437.09, bringing the contract total to $16,933,416.91.
What this record is
- Amount
- $16.9M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Waterworks Commission
- Introduced
- July 8, 2026
- Passed
- July 15, 2026