docketcity.com
0599-24

Subject: Final Payment Request on Contract W-21-2, 42" Water Main Replacement Phase 2, Super Excavators (Contractor) Staff Recommendation: To Approve Fiscal Note: Contract W-21-2 is complete at a final cost of $5,315,347.69.The contract achieved a 15.56% RWP compliance rate compared to the 20% RWP goal.

Communication Passed Introduced July 10, 2024

What this record is

Amount
$5.32M
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Waterworks Commission
Introduced
July 10, 2024
Passed
November 20, 2024