0544-26
Subject: Request for Final Payment (retainage) on Contract W-25-9, 2025 Water Main Replacement - Phase 3, Willkomm Excavating & Gracing, Inc. (contractor) Staff Recommendation: To Approve Fiscal Note: Contract W-25-9 is complete at a final cost of $506,309.40.
What this record is
- Held by
- Phase 3, Willkomm Excavating & Gracing, Inc 2 records across this site
- Amount
- $506K
- Runs until
- no end date published in this record
- Type
- contract
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Phase 3, Willkomm Excavating & Gracing, Inc also holds
Subject: Consideration of Change Order No. 2 on Contract W-25-9, 2025 Water Main Replacement - Phase 3, Willkomm Excavating & Gracing, Inc. (contracto…- Committee
- Waterworks Commission
- Introduced
- June 10, 2026
- Passed
- June 17, 2026