Subject: Bid Opening Results on Contract A-23, Chicory Road Area Sewer Improvements - Storage Tank Recommendation: To Approve Fiscal Note: The Utility received 4 bids and recommends that the project be awarded to the lowest, responsible bidder Miron Constuction, in the amount of $10,253,202.00. Engineer estimated costs $12M, $5,500,000 budgeted in 2024 CIP and $5,500,000 in 2025 (projected).
What this record is
- Amount
- $10.3M
- Runs until
- no end date published in this record
- Type
- bid
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Wastewater Commission
- Introduced
- May 10, 2024
- Passed
- May 21, 2024