Subject: Consideration of Change Order #4 on Contract D-22 Biogas Conditioning Project, Lee Mechanical (Contractor) Staff Recommendation: To Approve Fiscal Note: This is a zero-cost change order.

Communication Passed Introduced May 13, 2026
Committee
Wastewater Commission
Introduced
May 13, 2026
Passed
May 20, 2026