Subject: Consideration of Change Order No. 4 on Contract W-25-3 (rectifying), 2025 Water Main Replacement - Phase 2, Reesman's Excavating & Grading Inc. (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in a decrease of $23,026.90, bringing the total contract amount to $1,265,270.30.
What this record is
- Held by
- Phase 2, Reesman's Excavating & Grading Inc 2 records across this site
- Amount
- $1.27M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Phase 2, Reesman's Excavating & Grading Inc also holds
Subject: Request for Final Payment (retainage) on Contract W-25-3, 2025 Water Main Replacement - Phase 2, Reesman's Excavating & Grading Inc. (contrac…- Committee
- Waterworks Commission
- Introduced
- January 14, 2026
- Passed
- January 21, 2026