docketcity.com
90580

Change order No. 7 to Contract 8717, Mineral Point Road Widen Sidewalk (for East-West Bus Rapid Transit), to Parisi Construction, for $913,038.81to complete ordered improvements at the University Avenue and Babcock Drive railroad crossing. (District 5 and District 8)

Miscellaneous In Committee Introduced October 22, 2025

What this record is

Amount
$913K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
BOARD OF PUBLIC WORKS
Introduced
October 22, 2025
Passed
October 29, 2025

Where it was heard

BOARD OF PUBLIC WORKS Oct 29, 2025 Place On File Without Prejudice Pass