docketcity.com
87679

Change Order No. 1 to Contract 9289, Unit Well 19 Treatment System Addition, to Joe Daniels Construction Co., Inc., for $191,887322 (District 5).

Miscellaneous Approved Introduced March 24, 2025

What this record is

Held by
Joe Daniels Construction Co., Inc 19 records across this site
Amount
$191.9M
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Joe Daniels Construction Co., Inc also holds

Change Order No. 7 to Contract 9342, Well 15 PFAS Treatment Facility, to Joe Daniels Construction Co., Inc., for $271,561.06 (over contingency), and 2… $272K Madison, WI Subcontractor list for Contract 9740, Unit Well 12 Upgrade, to Joe Daniels Construction Co, Inc, for 59.78% (District 11) Madison, WI Change Order No. to Contract 9342, Well 15 PFAS Treatment Facility, to Joe Daniels Construction Co Inc, for $79,692.40. (District 12). $80K Madison, WI Change Order No. 3 to Contract 9289, Unit Well 19 Treatment System Addition, to Joe Daniels Construction Co., Inc., for $123,165.60 (District 5). $123K Madison, WI Change Order No. 5 to Contract 9342, Well 15 PFAS Treatment Facility, to Joe Daniels Construction Co Inc, for $0 and an additional 60 days for a compl… Madison, WI

All 19 records for Joe Daniels Construction Co., Inc →

Committee
BOARD OF PUBLIC WORKS
Introduced
March 24, 2025
Passed
April 2, 2025

Where it was heard

BOARD OF PUBLIC WORKS Apr 2, 2025 Approve Pass