Finance Committee

July 7, 2025 ·5:30 PM Final

Council Chambers, 6th Floor

Agenda — 16 items

  1. 1. Alderperson Croatt called the meeting to order at 5:30 p.m.
  2. 2. Pledge of Allegiance
  3. 3. Roll call of membership
  4. 4. Approval of minutes from previous meeting
  5. 5 Finance Committee Meeting Minutes June 9, 2025 25-0711 approved Pass
  6. 5. Public Hearing/Appearances
  7. 6. Action Items
  8. 8 Request to award sole source Engineering Bidding and Construction Services Contract to McMahon as part of Water Tower Booster Pump Improvements in the amount of $28,000 with a 10% contingency of $2,800 for a total not to exceed $30,800 25-0737 recommended for approval Pass
  9. 9 Request to award Unit DD-25 Mackville Quarry Grading & Capping contract to MCC, Inc., in the amount of $131,126.25 with a 15% contingency of $19,668.94 for a contract total not to exceed $150,795.19 25-0738 recommended for approval Pass
  10. 10 Request to approve 2026 sole source agreement with Baycom and Motorola Solutions for portable radios to receive promotional discount. 25-0751 recommended for approval Pass
  11. 11 Request to award sole source purchase of Appleton Wastewater Treatment Plant phosphorus analyzer to William Reid Ltd. for a total cost not to exceed $49,845 25-0779 recommended for approval Pass
  12. 12 Request to award contract to Advance Construction, Inc. for the Summer Street Lift Station Replacement Project in the amount of $1,194,000 with a 7.5% contingency of $89,550 for a project total not to exceed $1,283,550 25-0780 recommended for approval Pass
  13. 7. Information Items
  14. 14 Contract 126-24 was awarded to Rhode Bros for $563,500 with a contingency of $42,263 for the ORC Generator install. Change orders were approved totaling $39,135. Final contract amount is $602,635 with a contingency of $3,128. Payments issued to date total $587,569.12. Request final payment of $15,065.88. 25-0710 presented
  15. 15 Contract Unit H-25 was awarded to Norcon Corporation, Inc. for $203,946.00 with a contingency of $20,394.60 for Lawe Street Bridge over Fox River Repairs. Change orders were approved totaling an increase of $5,961.38. Final contract amount is $209,907.38. Payments issued to date total $199,412.01. Request final payment of $10,495.37 25-0781 presented
  16. 8. Adjournment adjourned Pass

Watch Appleton

This is one agenda. Appleton publishes another every few weeks, and the thing you care about is rarely on the one you happened to find. Name it and we will email you when it appears.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top