26-0785

Request to approve change order #1 to Kruczek Construction contract 3-26 Unit U-26 Sewer and Water Construction with an increase of $13,510.50 for a new contract total of $370,510.50 resulting in a decrease in contingency from $35,000 to $21,489.50.

Report Action Item Passed Introduced June 5, 2026

What this record is

Amount
$371K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Finance Committee
Introduced
June 5, 2026
On agenda
June 8, 2026
Passed
June 17, 2026

Where it was heard

Common Council Jun 17, 2026 approved Pass Finance Committee Jun 8, 2026 recommended for approval Pass