Contract 20-24 was awarded to Rohde Brothers for $720,840 with a contingency of $64,876 for the WWTP B-Bldg HVAC Improvements. Change orders were approved totaling $51,550. Final contract amount is $772,390 with a contingency of $13,326. Payments issued to date total $753,080.25. Request final payment of $19,309.75.