docketcity.com
25-1137

Contract 38-23 was awarded to SMA Construction Services for $6,705,000 with a contingency of $335,250 for Valley Transit Facility Renovation -Phase 1. Change orders were approved totaling $85,892.14. Final contract amount is $6,790,892.14 with a contingency of $249,357.86. Payments issued to date total $6,652,700. Request final payment of $138,192.14.

Report Action Item Action Item Introduced September 18, 2025

What this record is

Held by
SMA Construction Services
Amount
$6.79M
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Finance Committee
Introduced
September 18, 2025
On agenda
September 22, 2025
Passed
September 22, 2025

Where it was heard

Finance Committee Sep 22, 2025