25-1046

Contract 38-23 was awarded to SMA Construction Services for $6,705,000 with a contingency of $335,250 for Valley Transit Facility Renovation -Phase 1. Change orders were approved totaling $85,892.14. Final contract amount is $6,790,892.14 with a contingency of $249,357.86. Payments issued to date total $6,652,700. Request final payment of $138,192.14.

Report Action Item Action Item Introduced September 3, 2025
Committee
Finance Committee
Introduced
September 3, 2025
On agenda
September 22, 2025
Passed
September 22, 2025

Watch Appleton

Say what matters to you — a street, a company, a subject — and we will email you when Appleton files something about it.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.