Request to approve Change Order #1 to contract 106-25 Unit DD-25 Mackville Quarry Grading & Capping Project with MCC totaling $13,600 increase for a new contract total of $144,726.25 resulting in a decrease in contingency from $19,668.94 to $6,068.94

Report Action Item Passed Introduced August 21, 2025

What this record is

Amount
$145K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Finance Committee
Introduced
August 21, 2025
On agenda
August 25, 2025
Passed
September 3, 2025

Where it was heard

Common Council Sep 3, 2025 approved Pass Finance Committee Aug 25, 2025 recommended for approval Pass