Contract 59-24 was awarded to AMA Heating & AC for $467,042 with a contingency of $37,364 for Fire Station 1 & 6 HVAC improvements. Change orders were approved totaling $12,418. Final contract amount is $479,460 with a contingency of $37,364. Payments issued to date total $465,288.96. Request final payment of $14,171.04

Presentation Filed Introduced April 3, 2025

What this record is

Held by
AMA Heating & AC
Amount
$479K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Finance Committee
Introduced
April 3, 2025
On agenda
April 7, 2025
Passed
April 7, 2025

Where it was heard

Finance Committee Apr 7, 2025 received and filed