24-0846
Change Orders #17 and #18 to Miron Construction contract as part of the AWWTP Sludge Storage Building Addition Construction Project totaling $15,343.87, resulting in a decrease in contingency from $516,626.58 to $501,282.71
What this record is
- Amount
- $517K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Finance Committee
- Introduced
- June 21, 2024
- On agenda
- June 24, 2024
- Passed
- June 24, 2024