Change Orders #17 and #18 to Miron Construction contract as part of the AWWTP Sludge Storage Building Addition Construction Project totaling $15,343.87, resulting in a decrease in contingency from $516,626.58 to $501,282.71

Presentation Filed Introduced June 21, 2024

What this record is

Amount
$517K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Finance Committee
Introduced
June 21, 2024
On agenda
June 24, 2024
Passed
June 24, 2024

Where it was heard

Finance Committee Jun 24, 2024 received and filed