Request to approve Change Order #8 to Staab Construction contract as part of the AWWTP Phase I Belt Filter Press Equipment Upgrades Project totaling $66,293 resulting in a decrease in contingency from $675,538 to $609,245.

Report Action Item Passed Introduced June 21, 2024

What this record is

Amount
$676K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Finance Committee
Introduced
June 21, 2024
On agenda
June 24, 2024
Passed
July 17, 2024

Where it was heard

Common Council Jul 17, 2024 approved Pass Finance Committee Jun 24, 2024 recommended for approval Pass