Approval of Sole Source Engineering Services Contract to McMahon as part of the Appleton Water Treatment Facility Carbon Dioxide System Rehabilitation Project in the amount of $27,000 with a 10% contingency of $2,700 for a total not to exceed $29,700.

Report Action Item Passed Introduced May 1, 2024

What this record is

Amount
$30K
Runs until
no end date published in this record
Type
contract
Field
Professional services

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Utilities Committee
Introduced
May 1, 2024
On agenda
May 7, 2024
Passed
May 15, 2024

Where it was heard

Common Council May 15, 2024 approved Pass Utilities Committee May 7, 2024 recommended for approval Pass