24-0286
Change Orders #15 and #16 to Miron Construction contract as part of the AWWTP Sludge Storage Building Addition Construction Project totaling $5,379 resulting in a decrease in contingency from $522,005 to $516,626.
What this record is
- Amount
- $522K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Finance Committee
- Introduced
- March 8, 2024
- On agenda
- March 11, 2024
- Passed
- March 11, 2024