docketcity.com
RES 10638

Resolution authorizing execution of a Professional Services Supplemental Agreement (SA04) with WSP USA, Inc. in an amount up to $15,371,944.76, plus all applicable taxes, to develop final design and permitting, up to issuance of construction documents within the General Contractor - Construction Manager (GC-CM) project delivery framework governed by Chapter 39.10 RCW for the I-405 Crossing - Downtown to Eastrail project (CIP Plan No. G-126).

Resolution Consent Agenda Introduced March 18, 2026
Committee
City Council Regular Meeting
Requested by
City Manager's Office
Introduced
March 18, 2026
On agenda
June 2, 2026

Where it was heard

City Council Regular Meeting Jun 2, 2026