Ordinance approving a City requested deductive change order in the decreased amount of $337,667.92 for a revised total contract amount of $22,339,762.34 with J3 Company LLC for work associated with the construction of the drainage channel related to the Port San Antonio project, a 2017 Bond funded project.

Capital Improvements Passed Introduced June 9, 2021
Committee
City Council A Session
Requested by
Public Works Department
Introduced
June 9, 2021
On agenda
June 17, 2021
Passed
June 17, 2021
Enacted
June 17, 2021
Enactment no.
2021-06-17-0467