21-1108
Ordinance approving a City requested change order in the total increased amount of $583,146.80 and authorizing payment to Pesado Construction Company for construction of adjacent sidewalk projects related to the Cedarhurst Drive Area (Dumont Drive to Eaglerock Drive) project, a 2017 Bond funded project, located in Council District 4. Funds are available from 2017 - 2022 General Obligation Bond Program and are included in FY 2021 - FY 2026 Capital Improvement Program. [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Director, Public Works]
- Committee
- City Council A Session
- Requested by
- Public Works Department
- Introduced
- January 12, 2021
- On agenda
- February 18, 2021
- Passed
- February 18, 2021
- Enacted
- February 18, 2021
- Enactment no.
- 2021-02-18-0109