20-7277
Ordinance awarding a construction contract to E-Z Bel Construction, LLC in the amount of $5,269,274.41 with reimbursement from CPS Energy in an amount consistent with necessary adjustments to their existing infrastructure for the Brooks City Base Stinson Corridor (Research Plaza to South Presa Street) project, a 2017 Bond funded project. Funds are available from the 2017 - 2022 General Obligation Bond Program and are included in the FY 2021 - FY 2026 Capital Improvement Program. [Roderick Sanchez, Assistant City Manager; Razi Hosseini, Director, Public Works]
- Committee
- City Council A Session
- Requested by
- Public Works Department
- Introduced
- December 8, 2020
- On agenda
- February 4, 2021
- Passed
- February 4, 2021
- Enacted
- February 4, 2021
- Enactment no.
- 2021-02-04-0060