20-7035
Ordinance awarding a construction contract in the total amount of $3,973,933.97 to J. Sanchez Contracting, Inc., of which $60,595.68 will be reimbursed by the San Antonio Water System for the 2017 Bond Mission Road (San Antonio River to Southeast Military Drive) project; and, approving the appropriation and amending the FY 2021- FY 2026 Capital Improvements Program Budget with funds in the reimbursable amount of $1,131,305.00 from Mission Dive-In City TIRZ fund and $300,000.00 from the Airport Operating and Maintenance Fund for public improvements to the Mission Road (Southeast Military Drive to the San Antonio River) project.
- Committee
- City Council A Session
- Requested by
- Public Works Department
- Introduced
- November 24, 2020
- On agenda
- December 3, 2020
- Passed
- December 3, 2020
- Enacted
- December 3, 2020
- Enactment no.
- 2020-12-03-0843