Ordinance approving a contract with HJD Capital Electric, Inc., for Olmos Dam drain repairs at the Olmos Dam Gate House, for the Public Works Department for a total cost of $74,535.06. Funding is available through the FY 2021 - FY 2026 Capital Improvement Program. [Ben Gorzell, Chief Financial Officer; Troy Elliott, Deputy Chief Financial Officer, Finance]
What this record is
- Held by
- HJD Capital Electric, Inc
- Amount
- $75K
- Runs until
- no end date published in this record
- Type
- contract
- Field
- Utilities & energy
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- City Council A Session
- Requested by
- Finance Department
- Introduced
- November 4, 2020
- On agenda
- December 10, 2020
- Passed
- December 10, 2020
- Enacted
- December 10, 2020
- Enactment no.
- 2020-12-10-0878