Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 5 with Thalle Construction Co. Inc. for the BCRWWS - East Plant Expansion to 30 million gallons per day project.
What this record is
- Held by
- Thalle Construction Co 3 records across this site
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Thalle Construction Co also holds
Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 4 with Thalle Construction Co. Inc. for the BCRWWS - East … Discuss and consider action to approve a construction contract with Thalle Construction Company, Inc. in the amount of $12,795,000 associated with the…- Committee
- City Council
- Requested by
- Public Works
- Introduced
- June 9, 2025
- On agenda
- June 26, 2025
- Passed
- June 26, 2025