Bid No. 2025-051 - Construction Management-at-Risk (CMaR) Services for the remodel of two former Dallas County facilities. (Authorize the City Manager to finalize and execute a contract with Falkenberg Construction Company, Inc., in connection with the design (Phase I) of the remodel of two former Dallas County facilities in an amount not to exceed $20,000.00.)

Agenda Item Passed Introduced February 14, 2025

What this record is

Held by
Falkenberg Construction Company, Inc 8 records across this site
Amount
$20K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Falkenberg Construction Company, Inc also holds

Authorize the City Manager to finalize and execute Supplemental Agreement No. 1 (Phase II) to Bid No. 2025-051, Construction Manager-at-Risk (CMaR) Se… $5.54M Mesquite, TX Consider approving Resolution No. 2025-029 authorizing the City Manager to execute Change Order No. 2 for the construction contract for the Justice Ce… $423K Farmers Branch, TX Authorize the City Manager to finalize and execute Change Order Nos. 1 and 2 to Bid No. 2023-040, Construction Manager-at-Risk Services for the Constr… $250K Mesquite, TX Consider approving Resolution No. 2024-054 authorizing a contract with Falkenberg Construction Company with a fixed bid amount of $1,731,921, plus an … $1.73M Farmers Branch, TX Ordinance amending the FY2019/2020 Capital Improvements Projects Budget; Change Order/Amendment #1 with Falkenberg Construction for soil potasium chem… $26K Grand Prairie, TX

All 8 records for Falkenberg Construction Company, Inc →

Committee
City Council
Introduced
February 14, 2025
On agenda
March 3, 2025
Passed
March 3, 2025

Where it was heard

City Council Mar 3, 2025 Approved Pass